Capital projects

The City's 2023–2028 Community Investment Program lists 222 projects totalling $731,092,585.00 over five years. Only the first year, FY 2023/2024, is labelled funded.

Five-year total
$731.1M
Funded, FY 2023/2024
$136.0M
Projects
222
58 tied to a map area

Water, Sewer & Drainage

75 projects · $495,277,058.00

Project5-year total
Hollywood Road WWTF Second Treatment Train Design$309.0M
Lift Station No. 29 Relocation and Upsize$15.5M
Arterial Storm Sewer - Coulter Street - Hollywood Road to Sundown Lane$11.0M
WD Water Extensions and Improvements$10.0M
WWC Sewer Extensions and Improvements$7.5M
Replacement of Blowers, Motors and VFDs$6.9M
Digester Lid Replacement$6.5M
Lawrence Lake Pump Station$5.2M
Raw Water Reservoir Facility Rehab$5.1M
Olsen/Emil Storm Sewer$4.8M
Utility Billing Software Replacement$4.6M
Dissolved Air Floatation (DAF) Dewatering Project$4.5M
Air Scour for Filters$4.3M
WD Water Main Replacement Project (Small Mains)$4.0M
WWC Sewer Main Rehab Program$4.0M
Lawrence Lake Excavation$4.0M
Lawrence Lake West Slope Repair$4.0M
Storm Sewer System Extensions & Improvements$4.0M
Arterial Storm Sewer - 34th Avenue - Helium Road to Soncy Road$3.8M
Laboratory and Operator Room Remodel$3.6M
River Road Line Finished Water Reservoir$3.6M
Water Utility Compliance Administration$3.5M
McDonald Lake Dredging$3.4M
Medi-Park Lake Dredging$3.4M
Thompson Park Lake Dredging$3.4M
Playa 7 Pump Station$3.2M
Replace Bar Screen and Conveyor Replacement$2.6M
Sedimentation Basin Improvements$2.5M
Lamar Street at 45th Avenue$2.5M
Arterial Storm Sewer - Bell Street - Hollywood Road to Sundown Lane$2.5M
Drainage Channel from 58th Ave to McCarty Lake$2.4M
Georgia Street Construction$2.4M
RWR Pump Station Improvements$2.3M
Storm Sewer Farmers to I-27$2.1M
WD Water Main Valve Replacement$2.0M
Fulton and Bell 15-inch Storm Sewer$2.0M
Relocate MCC Electrical Panels$1.9M
WF Iso Valves and decommission 24'' collection line$1.6M
Osage Generators_H.S._Chem II_Portable$1.6M
Detritor upgrade No. 1 and No. 2$1.6M
Gravity Thickener & Gravity Thickener Collection Box Refurbishment$1.6M
Prod Carson County PS 1MG and 3MG interior and exterior paint$1.5M
Repaint Tank, Interior and Exterior for Pierce OHT$1.5M
Hollywood Scada System$1.3M
Chlorine System$1.3M
SPS Discharge line Repairs$1.0M
Blower Upgrade Project$1.0M
Polymer System Replacement$1.0M
Boiler Replacement$1.0M
34th and Grand Channel$1.0M
Coulter and Hillside Inlets$1.0M
CPS 15 & 16 Invertor Replacement$924.0K
Venturi Flow Meter Replacement at 34th TO and 34th PS$850.0K
Switchgear replacement at Bonham PS 5 & 6$750.0K
Dissolved Air Floatation (DAF) Building$750.0K
Flow Equalization Control Project$750.0K
45'' Venturi Replacement at Carson County Pump Station$700.0K
Tradewind Storm Sewer Engineering Study$600.0K
5-Year Corrosion Services$450.0K
SWT HVAC Chem II building replacement$400.0K
Lawrence Lake West Slope Repair Design$400.0K
River Road High Service Pumps No. 1, No. 2, No. 3$390.0K
WD Hydro Excavator$350.0K
Discharge meter at 24th PS$320.0K
JIB Crane and hoist Carson County$300.0K
East/West Blend Valves_TO2 Valve Replacement$275.0K
Bar Screen Replacement Headworks$250.0K
High Lift Hydraulic Check Valve Replacement$225.0K
CLA-VAL's Carson County$210.0K
Control Panels for Filter Gallery$150.0K
Building Roof Repair/Replace - Admin, Generator and Old Shop$100.0K
Chemical waste disposal and HAZMAT program$90.0K
Groundwater Availability Analysis$50.0K
Vehicle to access sampling sites$50.0K
New laboratory equipment$26.0K

Streets

37 projects · $91,606,950.00

Project5-year total
Arterial Reconstruction Program$14.0M
Street Resurfacing Program$14.0M
NE 24th Railroad Overpass Project$11.4M
Annual Street Resurfacing$10.3M
South Coulter from Hollywood to Sundown Lane$7.5M
34th Avenue from Soncy Road to Helium Road$7.5M
Barrio SE 10th Avenue Streetscape Improvement Project$5.5M
Bell Street from Attebury Drive to Sundown Lane$5.5M
Residential Resurfacing in Sections P9, Q9, Q10, R10$3.6M
Pavement Condition Assessment for Streets and Alleys$1.2M
Design Street Reconstruction$1.1M
Design Street Resurfacing$1.0M
Rotomill Machine$1.0M
Equipment for Additional Hot-Mix Laydown Operation$850.0K
Equipment for Additional Major Street and Alley Repair Crew$700.0K
SE 34th Avenue from RR Bridge to Osage$605.0K
Western Street from Arden Road to I-27$505.0K
Arden Road from Helium Road to Soncy$475.0K
Western Street from 34th Avenue to I-40$465.0K
Three Tandem-axle Dump Trucks with Operators$430.0K
Coulter Street from Amarillo Blvd to SW 9th$420.0K
Coulter Street from Arden Road to Hillside Road$415.0K
SW 34th Avenue from Bell Street to Western Street$410.0K
Equipment for Additional Minor Asphalt Repair Operation$370.7K
Crushing Recycled Asphalt$360.0K
NE 15th 16th Avenue from Mirror Street to Grand Street$325.0K
Hughes Street from SW 3rd Avenue to Amarillo Blvd.$280.0K
NE 15th 16th Avenue from Pierce Street to Mirror Street$250.0K
Evans Drive from West End to Coulter Street$185.0K
Pothole Patch Truck$175.0K
Street E&I$165.0K
Haul Truck and Trailer for Small Paving Machine$160.0K
Furnishings for New Street Offices in Service Center North Building$150.0K
Gem Lake Road from Avondale Street to Western Street$100.0K
Western Plaza Drive From Western to I-40$75.0K
Equipment for Small Area Sealing Crew$73.6K
Equipment for Additional Traffic Control Crew$57.2K

Airport

53 projects · $55,364,704.00

Project5-year total
TWY P/Associated Shoulders and Runway Blast Pad Rehabilitation - Design$8.2M
Construct Aircraft Apron$7.0M
CONRAC Phase 2 Light Maintenance$5.5M
Surface Parking Lot Expansion and Rehab Phase 3$4.0M
Construct Aircraft Hangar$4.0M
Rosenwald & Batson Reconstruction$3.1M
Rolling Hangar Repair Project$3.0M
GPU for PBB (2)$2.6M
Replace SRE/Station 10 Generator EA and Design$2.5M
ARFF Simulator EA and Design$2.4M
Construct New Connecting Taxiway$2.0M
SRE Snow Plow (2) includes EA and purchase$1.6M
Airport Master Plan Update$1.0M
ARFF Truck includes EA and Purchase$901.0K
Replace Terminal Air Handlers (1 of 13) Design, Construction, CA/RPR$700.0K
Aviation Facility Expansion EA$500.0K
Business Park EA$500.0K
Terminal Vestibule Refurb. Doors/Floors$450.0K
Replace (2) Automated Car Wash Units - Design$430.0K
Replace Terminal Carpets (concourse etc.)$400.0K
GIS Program Environmental Assessment$352.0K
Remodel Terminal Bathrooms$350.0K
Baggage Handling System Design$300.0K
Aerial Lift 150'$285.0K
Front Entrance Enhancements$200.0K
Re-glaze Select Terminal Exterior Windows$200.0K
Airport Perimeter Fence Repairs and Improvements (Environmental)$185.0K
Replace/Repair Airfield Perimeter Road and Service Routes (Environmental)$185.0K
Airport Capital Program E&I$177.8K
Install Terminal Water Softener System$150.0K
ARFF Crash Phone System (Environmental + Design)$140.0K
Pavement Condition Index / Pavement Management Plan Update$136.0K
Grasslands Restoration Plan (WHMP) Environmental Assessment$135.0K
Pavement Condition Index / Pavement Management Plan Update$135.0K
Purchase Paint Striping Machine$130.0K
Tug HS Doors and Add Man Door on West Side$106.0K
4X4 Utility Vehicle with implements$105.0K
Building 602 Maintenance$100.0K
Fork Lift$100.0K
Replace Airport Computers$100.0K
Replace Servers / IT equipment$100.0K
Skid Steer w/ Implements$100.0K
Update Paging / FIDS Equipment$100.0K
Various Software Upgrades$100.0K
North Ramp Business Park Needs Assessment$100.0K
Facilities Truck (2)$90.0K
Facilities Service Truck (2)$85.0K
Mini Ride-On Sweeper$80.0K
Scissor Lift Replacement$80.0K
Police Unit$75.0K
Tank Removal at Marcee Hangar$70.0K
Runway Rubber Removal Project$40.0K
Rubber Removal$40.0K

General Facilities

37 projects · $42,559,681.00

Project5-year total
Fire Department Facilities Master Plan Project Construction Fund$8.0M
Parks Maintenance Equipment & Improvements (E&I)$7.5M
Aircraft Rescue Training Center$4.2M
Traffic Signal System Improvements (E&I)$2.7M
Self-Contained Breathing Apparatus (SCBA) Replacement$2.0M
Upfitting Patrol Vehicles$2.0M
AM&W Kennel Renovation$1.7M
Facilities Capital Maintenance E&I$1.6M
Patrol Vehicles$1.4M
Replace Overhead Doors$1.1M
Firefighter Protective Clothing$900.0K
Document Conversion$878.5K
AECC Remodel$700.0K
Establish ADA Concrete Pads for Transit Stops$700.0K
Fire Apparatus Equipment$650.0K
AISD School Liaison Vehicles$640.0K
Fire Department Facilities Master Plan Land Acquisition Fund$500.0K
Fire Department Facilities Master plan Project Design Fund$500.0K
EMS Cardiac Monitors$475.0K
Transit Route 4142 bus stop infrastructure improvements$400.0K
Fire Department Facilities Master Plan$400.0K
CISD School Liaison Vehicle$364.0K
Bike Rack Project$350.0K
Bus Shelter Replacement$350.0K
Pavement Markings (E&I)$318.5K
Car Wash Repair/Upgrade$300.0K
Training Facility E&I$300.0K
Automated External Defibrillator AED Replacement$277.0K
Arterial Street Lights New Developments$270.0K
Fire Station 14 FFE$250.0K
Amarillo Fire Department Grants$205.0K
Siren System Expansion Project$200.0K
Refresh Courtroom Lobby$165.0K
Traffic Master Plan$140.0K
Narcotics Vehicle (Class 111)$138.0K
Install Armory Vault at Shooting Complex$59.9K
Shelter Services Building Remodel$59.8K

Fleet

1 projects · $31,000,000.00

Project5-year total
Equipment Replacement$31.0M

Other

1 projects · $7,929,192.00

Project5-year total
Residential Dumpster Replacement Program$7.9M

Civic Center & Convention

17 projects · $4,855,000.00

Project5-year total
Auditorium Elevator$800.0K
Stage Level Dressing Rooms/Dock$740.0K
Parking Lot Improvements$690.0K
Hockey/Football Improvements$615.0K
Recycling Program$350.0K
Staging Component Replacement$250.0K
Grand Plaza Fountain Replacement$215.0K
Table Replacements$200.0K
Dock No. 7 Replacement$180.0K
New Basketball Floor$165.0K
New I.T. Switch and Fiber Upgrade$150.0K
Wall Treatment Replacement in Auditorium$150.0K
Interior/Exterior Signage Program$100.0K
Media Blasting of Brick Walls$100.0K
Ice Plant Repairs$70.0K
Coliseum Steel Modifications$50.0K
Overhead Door Replacement$30.0K

Information Technology

1 projects · $2,500,000.00

Project5-year total
Information Technology E&I$2.5M