Skip to content
AmarilloBudget · Contracts · Debt

Capital project · Water, Sewer & Drainage

East/West Blend Valves_TO2 Valve Replacement

Amarillo's 2023–2028 capital plan programs $275,000.00 for this project over five years, of which $0.00 is in the funded first year.

Replacement of the Bonham PS east and west end valves. This also includes replacement of the TO2 valve connecting 34th PS and Bonham PS. Each unit includes replacement of valve actuators.
Project description as written in the City's plan (p. 111).
Five-year total
$275.0K
Funded, FY 2023/2024
$0
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$0.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$275,000.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Water Production
Division
Water Utilities
Fund
Water and Sewer System Fund
Council pillar
Public Safety
City Manager initiative
Implementation of Best Practices

Other Water Production projects

Project detail: page 111 of the plan.