Prod Carson County PS 1MG and 3MG interior and exterior paint

Amarillo's 2023–2028 capital plan programs $1,500,000.00 for this project over five years, of which $0.00 is in the funded first year.

Engineer and design project for interior and exterior painting needed on (2) steel storage tanks at Carson County pump station. Tank sizes are 1 MG and 3 MG.
Project description as written in the City's plan (p. 115).
Five-year total
$1.5M
Funded, FY 2023/2024
$0
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$0.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$0.00
FY 2026/2027Approved, unfunded$1,500,000.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Water Production
Division
Water Utilities
Fund
Water and Sewer System Fund
Council pillar
Economic Development & Redevelopment
City Manager initiative
Implementation of Best Practices

Other Water Production projects

Project detail: page 115 of the plan.