Capital project · Water, Sewer & Drainage · No. 560000
Storm Sewer System Extensions & Improvements
Amarillo's 2023–2028 capital plan programs $4,000,000.00 for this project over five years, of which $800,000.00 is in the funded first year.
This funding is for drainage related system expansions and Improvements throughout the city. Work will involve repair of storm sewer lines, inlets, replacement of culverts, regrading of ditches erosion control and playa lake maintenance.
- Five-year total
- $4.0M
- Funded, FY 2023/2024
- $800.0K
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $800,000.00 | |
| FY 2024/2025 | Approved, unfunded | $800,000.00 | |
| FY 2025/2026 | Approved, unfunded | $800,000.00 | |
| FY 2026/2027 | Approved, unfunded | $800,000.00 | |
| FY 2027/2028 | Approved, unfunded | $800,000.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Drainage Utility
- Division
- Water Utilities
- Fund
- Drainage Utility Fund
- Council pillar
- Fiscal Responsibility
- City Manager initiative
- Implementation of Best Practices
Other Drainage Utility projects
Project detail: page 239 of the plan.