Capital project · Water, Sewer & Drainage · No. 560176
Arterial Storm Sewer - 34th Avenue - Helium Road to Soncy Road
Amarillo's 2023–2028 capital plan programs $3,758,300.00 for this project over five years, of which $0.00 is in the funded first year.
Design and construction of storm sewer and all associated features in conjunction with the improvement of 34th Avenue to a full arterial section from Helium Road to Soncy Road.
- Five-year total
- $3.8M
- Funded, FY 2023/2024
- $0
- Area
- SW
- Map grid H-13
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $0.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $3,758,300.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Drainage Utility
- Division
- Water Utilities
- Fund
- Drainage Utility Fund
- Council pillar
- Economic Development & Redevelopment
- City Manager initiative
- Implementation of Best Practices
Other Drainage Utility projects
Project detail: page 242 of the plan.