Capital project · Water, Sewer & Drainage · No. 523499
Replacement of Blowers, Motors and VFDs
Amarillo's 2023–2028 capital plan programs $6,916,000.00 for this project over five years, of which $0.00 is in the funded first year.
Replacing current blowers with high capacity blower system with variable speed capabilities to meet median requirements for bio-nutrient removal, as well as easier adaptation to future needs and innovations in technology.
- Five-year total
- $6.9M
- Funded, FY 2023/2024
- $0
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $0.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $1,635,000.00 | |
| FY 2026/2027 | Approved, unfunded | $5,281,000.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- River Road Water Reclamation
- Division
- Water Utilities
- Fund
- Water and Sewer System Fund
- Council pillar
- Customer Service
- City Manager initiative
- Implementation of Best Practices
Other River Road Water Reclamation projects
Project detail: page 148 of the plan.