Capital project · Water, Sewer & Drainage
Detritor upgrade No. 1 and No. 2
Amarillo's 2023–2028 capital plan programs $1,580,000.00 for this project over five years, of which $0.00 is in the funded first year.
Replacement of motor assembly, bearings/gears and shafts, rake assembly and catwalks. Add safety railing and fall protection screens. Replace or repair eroded concrete. Add alarm control panels. Replacement of cast iron gates with stainless steel.
- Five-year total
- $1.6M
- Funded, FY 2023/2024
- $0
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $0.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $0.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $1,580,000.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- River Road Water Reclamation
- Division
- Water Utilities
- Fund
- Water and Sewer System Fund
- Council pillar
- Customer Service
- City Manager initiative
- Implementation of Best Practices
Other River Road Water Reclamation projects
Project detail: page 152 of the plan.