Capital project · Water, Sewer & Drainage · No. 523494
Raw Water Reservoir Facility Rehab
Amarillo's 2023–2028 capital plan programs $5,145,000.00 for this project over five years, of which $0.00 is in the funded first year.
Drain Raw Water Reservoir (RWR) and remove and replace 2.1 million sq ft 80 MIL HDPE liner. Replace 60" flow meter, replace (3) suction isolation valves, upgrade MCC, panels and PLC switchgear for the Raw Water Reservoir Facility.
- Five-year total
- $5.1M
- Funded, FY 2023/2024
- $0
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $0.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $0.00 | |
| FY 2026/2027 | Approved, unfunded | $350,000.00 | |
| FY 2027/2028 | Approved, unfunded | $4,795,000.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Water Transmission
- Division
- Water Utilities
- Fund
- Water and Sewer System Fund
- Council pillar
- Public Safety
- City Manager initiative
- Implementation of Best Practices
Other Water Transmission projects