Lift Station No. 29 Relocation and Upsize

Amarillo's 2023–2028 capital plan programs $15,500,000.00 for this project over five years, of which $0.00 is in the funded first year.

Lift Station 29 located at 8016 E I-40 has been overloaded per the 2013 master plan study. The lift station is also land locked so expanding would be difficult. The master plan showed that we could move the station to 34th and Lakeside area then install a force main to Whitaker and 34th.
Project description as written in the City's plan (p. 138).
Five-year total
$15.5M
Funded, FY 2023/2024
$0
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$0.00
FY 2024/2025Approved, unfunded$15,500,000.00
FY 2025/2026Approved, unfunded$0.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Waste Water Collection
Division
Water Utilities
Fund
Water and Sewer System Fund
Council pillar
Customer Service
City Manager initiative
Implementation of Best Practices

Other Waste Water Collection projects