Amarillo's 2023–2028 capital plan programs $2,100,000.00 for this project over five years, of which $2,100,000.00 is in the funded first year.
First phase of a project to extend storm sewer from Farmers and Western to capture existing storm sewer in Bell Street and reduce the drainage basin for Lawrence Lake by diverting runoff to McCarty Lake.
- Five-year total
- $2.1M
- Funded, FY 2023/2024
- $2.1M
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $2,100,000.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $0.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Drainage Utility
- Division
- Water Utilities
- Fund
- Drainage Utility Fund
- Council pillar
- Economic Development & Redevelopment
- City Manager initiative
- Implementation of Best Practices
Other Drainage Utility projects
Project detail: page 238 of the plan.