Capital project · General Facilities · No. 411116

Pavement Markings (E&I)

Amarillo's 2023–2028 capital plan programs $318,549.00 for this project over five years, of which $60,000.00 is in the funded first year.

Thermoplastic materials and labor needed to replace pavement markings and bike lane markings, such as parking stall lines in the central business district used for paid parking, bike lanes and pavement markings (bikes, arrows). These materials are lasting about 2-3 years in the central business district.
Project description as written in the City's plan (p. 24).
Five-year total
$318.5K
Funded, FY 2023/2024
$60.0K
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$60,000.00
FY 2024/2025Approved, unfunded$61,800.00
FY 2025/2026Approved, unfunded$63,654.00
FY 2026/2027Approved, unfunded$65,564.00
FY 2027/2028Approved, unfunded$67,531.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Traffic Administration
Division
Public Works
Fund
General Construction Fund
Council pillar
Transportation
City Manager initiative
Implementation of Best Practices

Other Traffic Administration projects

Project detail: page 24 of the plan.