Capital project · Streets · No. 410325
Equipment for Additional Hot-Mix Laydown Operation
Amarillo's 2023–2028 capital plan programs $850,000.00 for this project over five years, of which $850,000.00 is in the funded first year.
1/2 ton Truck (Cat 208), 24,000 GVW Truck w/ dump bed (Cat 321), 42,000 GVW Truck w/ 5th Wheel (Cat 320), Two 52,000 GVW Trucks w/ 12 yd dump bed (Cat 361), Asphalt Laydown Machine (Cat 600), 3 ton Vibratory Steel Wheel Roller (Cat 516), Tilt Bed Trailer (Cat 717), Flatbed Trailer (Cat 701), Vibratory Compactor (Cat 401)
- Five-year total
- $850.0K
- Funded, FY 2023/2024
- $850.0K
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $850,000.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $0.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Project Number: 410325
- Division
- Water Utilities
- Fund
- Street Improvement Fund
- Council pillar
- Transportation
- City Manager initiative
- Implementation of Best Practices
Project detail: page 56 of the plan.