Capital project · Water, Sewer & Drainage
Lawrence Lake West Slope Repair Design
Amarillo's 2023–2028 capital plan programs $400,000.00 for this project over five years, of which $400,000.00 is in the funded first year.
Lawrence Lake excavation & bank stabilization planning and design.
- Five-year total
- $400.0K
- Funded, FY 2023/2024
- $400.0K
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $400,000.00 | |
| FY 2024/2025 | Approved, unfunded | $0.00 | |
| FY 2025/2026 | Approved, unfunded | $0.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Drainage Utility
- Division
- Water Utilities
- Fund
- Drainage Utility Fund
- Council pillar
- Economic Development & Redevelopment
- City Manager initiative
- Implementation of Best Practices
Other Drainage Utility projects
Project detail: page 233 of the plan.