Skip to content
AmarilloBudget · Contracts · Debt

Capital project · Water, Sewer & Drainage

CPS 15 & 16 Invertor Replacement

Amarillo's 2023–2028 capital plan programs $924,000.00 for this project over five years, of which $0.00 is in the funded first year.

Replace Eaton invertors for the switchgears used to operate pumps 15 and 16 at the Combined Pump Station. Project to include sending off pumps and motors for preventative maintenance and conditioning.
Project description as written in the City's plan (p. 128).
Five-year total
$924.0K
Funded, FY 2023/2024
$0
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$0.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$924,000.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Surface Water Treatment Osage Water Plant
Division
Water Utilities
Fund
Water and Sewer System Fund
Council pillar
Public Safety
City Manager initiative
Implementation of Best Practices

Other Surface Water Treatment Osage Water Plant projects

Project detail: page 128 of the plan.