Capital project · Water, Sewer & Drainage
Air Scour for Filters
Amarillo's 2023–2028 capital plan programs $4,350,000.00 for this project over five years, of which $0.00 is in the funded first year.
Plan and design building location, blower system, piping and functionality that could be tied into and optimize treatment process in filters. Designed to increase loading rates, filter run times and to save water in backwashing.
- Five-year total
- $4.3M
- Funded, FY 2023/2024
- $0
- Area
- Citywide
Estimated capital expenditure
| Fiscal year | Status in plan | Amount | |
|---|---|---|---|
| FY 2023/2024 | Approved, funded | $0.00 | |
| FY 2024/2025 | Approved, unfunded | $600,000.00 | |
| FY 2025/2026 | Approved, unfunded | $3,750,000.00 | |
| FY 2026/2027 | Approved, unfunded | $0.00 | |
| FY 2027/2028 | Approved, unfunded | $0.00 |
The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".
In the plan
- Department
- Surface Water Treatment Osage Water Plant
- Division
- Water Utilities
- Fund
- Water and Sewer System Fund
- Council pillar
- Public Safety
- City Manager initiative
- Implementation of Best Practices
Other Surface Water Treatment Osage Water Plant projects
Project detail: page 127 of the plan.