Skip to content
AmarilloBudget · Contracts · Debt

Capital project · Streets

Street E&I

Amarillo's 2023–2028 capital plan programs $165,000.00 for this project over five years, of which $165,000.00 is in the funded first year.

Funding for emergency and unexpected needs for streets, and street infrastructure extensions and improvements in the city's street system.
Project description as written in the City's plan (p. 65).
Five-year total
$165.0K
Funded, FY 2023/2024
$165.0K
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$165,000.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$0.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Project Number: 000000
Division
Water Utilities
Fund
Street Improvement Fund
Council pillar
Transportation
City Manager initiative
Implementation of Best Practices

Project detail: page 65 of the plan.