Amarillo's 2023–2028 capital plan programs $430,000.00 for this project over five years, of which $0.00 is in the funded first year.

Three 52,000 GVW Tandem-Axle Trucks with Dump Beds (Cat. 361)
Project description as written in the City's plan (p. 79).
Five-year total
$430.0K
Funded, FY 2023/2024
$0
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$0.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$430,000.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Project Number: 000000
Division
Water Utilities
Fund
Street Improvement Fund
Council pillar
Transportation
City Manager initiative
Implementation of Best Practices

Other Project Number: 000000 projects