Skip to content
AmarilloBudget · Contracts · Debt

Capital project · Airport · No. 540353

Pavement Condition Index / Pavement Management Plan Update

Amarillo's 2023–2028 capital plan programs $135,000.00 for this project over five years, of which $135,000.00 is in the funded first year.

Engineering analysis of the condition of the Airport's airfield pavements (runways, taxiways, air carrier ramp) and update to the required Pavement Management Plan. Requires environmental assessment in FY 2022 with expected project completion in FY 2023.
Project description as written in the City's plan (p. 180).
Five-year total
$135.0K
Funded, FY 2023/2024
$135.0K
Area
NE
Map grid V-10

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$135,000.00
FY 2024/2025Approved, unfunded$0.00
FY 2025/2026Approved, unfunded$0.00
FY 2026/2027Approved, unfunded$0.00
FY 2027/2028Approved, unfunded$0.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Airport
Division
Airport
Fund
Airport Fund
Council pillar
Transportation
City Manager initiative
Implementation of Best Practices

Other Airport projects

Project detail: page 180 of the plan.