Skip to content
AmarilloBudget · Contracts · Debt

Capital project · General Facilities · No. 410716

Fire Apparatus Equipment

Amarillo's 2023–2028 capital plan programs $650,000.00 for this project over five years, of which $120,000.00 is in the funded first year.

This is intended to fund items that are installed on a new fire vehicle before it is put into service or replace end of life items. These items are not dealer furnished, such as department decals or vehicle wraps, emergency control devices, mobile computer docking stations, Fire Fleet Services fabrication materials, etc.
Project description as written in the City's plan (p. 37).
Five-year total
$650.0K
Funded, FY 2023/2024
$120.0K
Area
Citywide

Estimated capital expenditure

Fiscal yearStatus in planAmount
FY 2023/2024Approved, funded$120,000.00
FY 2024/2025Approved, unfunded$125,000.00
FY 2025/2026Approved, unfunded$130,000.00
FY 2026/2027Approved, unfunded$135,000.00
FY 2027/2028Approved, unfunded$140,000.00

The plan labels the first year "Approved Funded" and each later year "Approved Unfunded".

In the plan

Department
Department: 1910 - Fire Operations
Division
Amarillo Fire Department
Fund
General Construction Fund
Council pillar
Public Safety
City Manager initiative
Implementation of Best Practices

Other Department: 1910 - Fire Operations projects

Project detail: page 37 of the plan.