Amarillo's sewer collection system: reported overflows and main and lift station work (2017-2026)

Amarillo's wastewater collection system (sewer mains, manholes and lift stations) has had a series of reported overflows of untreated wastewater. City releases and local news report a 980,000-gallon and a 50,000-gallon overflow from an Osage Street manhole in June 2023, an 850,000-gallon lift station overflow near South Osage in July 2023, five overflows at Lift Station 40 (7100 Cliffside) between December 2023 and September 2026 ranging from 100,000 to about 1,026,000 gallons, and a 750,000-gallon discharge from a sewer main manhole that reached East Amarillo Creek on September 11, 2026, after which the City advised against recreational contact with Thompson Park Lake. TCEQ was notified of each. Council records from 2017 on show collection-system work, including an emergency sewer main replacement ($355,000, 2017), pipe-bursting sewer main rehabilitation contracts (about $1.9 million each in 2017, 2017-18 and 2022), a TWDB-financed Lift Station 32 replacement, design of a new Lift Station 40 (2019), Lift Station 40 pumps (2024), and a Lift Station 19 replacement study on the October 13, 2026 agenda. The City has not publicly tied these purchases to specific overflows.

A storyline groups dated events in order. It is a chronology, not an argument; it does not say why anything happened. All storylines

Where the story starts depends on the framing

  1. · Precursor

    Council approves $355,000 emergency replacement of a sewer main feeding Lift Station 12

    On consent, the council approved, 5-0, an emergency replacement of the sewer main at 35th Avenue and Taylor Street that discharges into Lift Station 12, awarded to Amarillo Utility Contractors for $355,000. The staff memo said the line had stoppages, crews had removed mud and pieces of concrete pipe from the lift station, and a collapse of the main was possible.[1][2]

    Amarillo Utility Contractors

    • ✓ Verified

      The February 28, 2017 consent agenda included approval of the emergency replacement of a sewer main at 35th Avenue and Taylor Street discharging into Lift Station 12, by Amarillo Utilities Contractors for $355,000; the minutes record the consent agenda approved 5-0.[1][2]

      Contract
      $355,000
    • ✓ Verified

      City staff (agenda transmittal memo): The staff memo said the line ran through an alley and under an existing structure, had stoppages, that crews had spent many hours removing mud and pieces of concrete pipe from the lift station, and that a void might exist and a total collapse was possible, which would require 24-hour bypass pumping.[1]

  2. · Context

    Council awards $1,898,269 pipe-bursting sewer main rehabilitation contract

    The council voted 5-0 to approve a construction contract with Vaught Services, Inc. ($1,898,269 per the agenda) to replace select sanitary sewer lines by pipe bursting at locations identified by the Wastewater Collection Department.[3][4]

    • ✓ Verified

      The August 22, 2017 agenda lists the award of the FY16-17 Sewer Main Rehab by Pipe Bursting contract (Bid No. 5800) to Vaught Services, Inc. for $1,898,269, to replace select sanitary sewer lines in areas identified by the Wastewater Collection Department; the minutes record approval 5-0.[3][4]

      Contract
      $1,898,269
  3. · Context

    Council authorizes a $12.5 million TWDB loan application to replace Lift Station 32

    The council voted 5-0 (Resolution No. 08-22-17) to apply to the Texas Water Development Board's Clean Water State Revolving Fund for an additional $12,500,000 to replace Lift Station 32 on Osage Street. A June 2018 City memo says TWDB approved the $12,500,000 loan commitment on March 6, 2018.[3][4][5]

    • ✓ Verified

      On August 22, 2017 the council voted 5-0 to approve submitting a TWDB Clean Water State Revolving Fund loan application for an additional $12,500,000 to replace Lift Station 32; the item said $2,615,473 remained available for construction from earlier TWDB project[3][4]

      Loan application
      $12,500,000
      Prior funds available
      $2,615,473
    • ✓ Verified

      A City finance memo for the June 19, 2018 council meeting said the City had received a $12,500,000 loan commitment from TWDB's Clean Water State Revolving Fund, approved March 6, 2018, to finance Lift Station 32 construction through Waterworks and Sewer System Revenue Bonds, New Series 2018A.[5]

      Twdb commitment
      $12,500,000
  4. · Context

    Council awards $519,200 Kimley-Horn contract to design a new Lift Station 40

    The council voted 5-0 to award Kimley-Horn and Associates an engineering services agreement of $519,200 for the design of a new Lift Station 40, the station at 7100 Cliffside where later overflows were reported.[6][7]

    Kimley-Horn and Associates

    • ✓ Verified

      On February 26, 2019 the council voted 5-0 to award Kimley-Horn and Associates, Inc. the engineering services agreement for the design of a new Lift Station 40; the agenda lists the amount as $519,200.[6][7]

      Contract
      $519,200
  5. · Context

    Council approves the contract to reconstruct Lift Station 32 on Osage

    The council voted 5-0 to award a contract to reconstruct Lift Station 32 and associated sewer lines in southeast Amarillo. NewsChannel 10 reported the station was built in 1964, handles about 3 million gallons a day, was at capacity, and that the project would bypass and eliminate Lift Station 33; TWDB funds most of the project, with a $150,000 City share.[8][9]

    Jared Miller

    • ✓ Verified

      On June 25, 2019 the council voted 5-0 to award a contract for the reconstruction of Lift Station No. 32 and associated sewer lines to serve southeast Amarillo, expand the service area and upgrade the system. The minutes do not state the contract amount.[8]

    • ✓ Verified

      NewsChannel 10 reported that Lift Station 32 was built in 1964, handles about 3 million gallons of sewage a day and was at capacity; the reconstruction adds capacity and bypasses and eliminates Lift Station 33; TWDB funds most of the project, and the City's share is $150,000 from its Extension and Improvement Fund.[9]

      City share
      $150,000
    • ✓ Verified

      Jared Miller: City Manager Jared Miller said, as reported by NewsChannel 10: "If we don't approve, we still need to do the project, but it would cost us quite a bit more."[9]

  6. · Context

    Change order brings the FY2017-18 pipe-bursting sewer rehabilitation contract to $2,103,134

    The June 9, 2020 consent agenda included Change Order No. 3 ($18,620) to the FY2017-2018 Sewer Main Rehabilitation by Pipe Bursting contract with PM Construction & Rehab LLC dba IPR South Central, raising it from an original $1,886,030 to $2,103,134, for additional sewer main replacement near Oldham Circle and Southwest 32nd Avenue.[10]

    • ✓ Verified

      The June 9, 2020 minutes list, among consent items moved for approval as presented, Change Order No. 3 ($18,620) to the FY2017-2018 Sewer Main Rehabilitation by Pipe Bursting contract with PM Construction & Rehab LLC dba IPR South Central: original contract $1,886,030, previous change orders $198,484, revised total $2,103,134. The scanned minutes page does not show a vote tally for the consent agenda.[10]

      Original contract
      $1,886,030
      Revised contract
      $2,103,134
      Previous change orders
      $198,484
      Change order 3
      $18,620
  7. · Context

    Council awards $1,925,095 sewer main pipe-bursting contract to King Solution Services

    The council approved, 5-0 on consent, a $1,925,095 construction contract with King Solution Services to install new six-inch sanitary sewer main by pipe bursting, with sewer taps and manholes. A May 23, 2023 change order raised it to $1,984,049.[11][12]

    King Solution Services

    • ✓ Verified

      On March 8, 2022 the council approved its consent agenda 5-0, including the award of a $1,925,095 construction services contract to King Solution Services to install new six-inch sanitary sewer main by pipe bursting, with sewer taps and manholes.[11]

      Contract
      $1,925,095
    • ✓ Verified

      On May 23, 2023 the council approved, 4-0 on consent, Change Order No. 1 ($58,954) to the King Solution Services pipe-bursting contract, for a total revised award of $1,984,049.[12]

      Change order
      $58,954
      Revised contract
      $1,984,049
    • ✓ Verified

      The City's check register records $1,982,246.50 in 11 payments to King Solution Services LLC between 2022-08-25 and 2023-10-26. The register does not identify the project each payment funded.[13]

      Register total
      $1,982,247

      See the payments in the check register →

  8. · Origin

    Osage Street manhole overflows twice during June 2023 storms

    The City reported that a manhole at 5601 S. Osage Street overflowed on June 1, 2023 after five lift stations backed up, releasing about 980,000 gallons, and overflowed again on June 2 during heavy rain, releasing an estimated 50,000 gallons of untreated wastewater. TCEQ was notified. These were collection-system overflows, separate from the Hollywood Road plant spills the same week.[14][15]

    • ✓ Verified

      According to the City, the manhole at 5601 S. Osage Street overflowed at 5:30 a.m. on Thursday, June 1, 2023 after five lift stations backed up in a cascade, releasing about 980,000 gallons; the spill was contained at 2:45 p.m.[14]

      Gallons
      980,000
    • ✓ Verified

      The same manhole overflowed again from 6:30 p.m. to 11:15 p.m. on Friday, June 2, 2023, releasing an estimated 50,000 gallons of untreated wastewater; the City attributed it to heavy rainfall, said crews vacuumed the wastewater and applied HTH to the residue, and said TCEQ was notified.[14][15]

      Gallons estimated
      50,000
  9. · Related development

    Lift station failure near South Osage releases about 850,000 gallons

    The City reported that a mechanical failure at a lift station near South Osage Street and Southeast 58th Avenue caused a manhole to overflow, releasing about 850,000 gallons of untreated wastewater; cleanup was complete by 9 a.m. on July 3, 2023. TCEQ was notified.[16]

    • ✓ Verified

      NewsChannel 10 reported on July 3, 2023 that a mechanical failure at a lift station near South Osage Street and Southeast 58th Avenue caused a manhole to overflow; the City said about 850,000 gallons of untreated wastewater was released and cleaned up by 9 a.m. that day, and that TCEQ was notified.[16]

      Gallons
      850,000
  10. · Related development

    Coupler failure at the Cliffside lift station releases 1,026,000 gallons

    ABC 7 reported on December 11, 2023 that, according to the City, a mechanical failure of a coupler caused a manhole overflow at the lift station at 7100 Cliffside Road, releasing 1,026,000 gallons of untreated wastewater. Crews vacuumed most of it and chlorinated the rest; TCEQ was notified.[17]

    • ✓ Verified

      ABC 7 reported on December 11, 2023 that, according to the City, a "wastewater overflow" from a manhole at the lift station at 7100 Cliffside Road was caused by a mechanical failure of a coupler and released 1,026,000 gallons of untreated wastewater; cleanup was completed around 8 p.m. The article does not state the date the overflow began.[17]

      Gallons
      1,026,000
  11. · Related development

    Pump bearing failure at the Cliffside lift station releases 100,000 gallons

    ABC 7 reported a 100,000-gallon spill of untreated wastewater at the Cliffside Lift Station, 7100 Cliffside Road, starting at 11:45 a.m. on Tuesday (July 2, 2024) and contained by 2 p.m., caused by the failure of a mechanical pump bearing. It did not reach natural waters; TCEQ was notified.[18]

    • ✓ Verified

      ABC 7 reported that 100,000 gallons of untreated wastewater spilled at the Cliffside Lift Station from 11:45 a.m. to 2 p.m. on Tuesday (July 2, 2024), caused by the failure of a mechanical pump bearing; it did not reach natural waters, the discharge was disinfected with HTH, and TCEQ was notified.[18]

      Gallons
      100,000
  12. · Related development

    945,000 gallons discharged at the Cliffside lift station

    The City reported a 945,000-gallon discharge of untreated wastewater at the lift station at 7100 Cliffside that began at 7 p.m. on September 16, 2024, was observed at 1:30 p.m. on September 17 and was contained at 2:30 p.m. The City gave the cause as trash collected inside the pump and an alarm system failure. TCEQ was notified.[19][20]

    • ✓ Verified

      The City reported a 945,000-gallon discharge of untreated wastewater at the lift station at 7100 Cliffside, beginning at 7 p.m. on September 16, 2024, observed at 1:30 p.m. on September 17 and contained at 2:30 p.m.[19][20]

      Gallons
      945,000
    • ✓ Verified

      City of Amarillo: The City gave the cause as trash collected inside the pump and an alarm system failure, said remediation and disinfection were complete, and said TCEQ had been notified.[19][20]

  13. · Context

    Council approves $90,274.56 purchase of two pumps for Lift Station 40

    On consent (approved 5-0), the council approved buying two Fairbank Morse pumps for Lift Station 40 from AAW Pumps Motors Controls through BuyBoard for $90,274.56, funded from water and sewer fund revenues.[21][22]

    Michael Price

    • ✓ Verified

      The December 10, 2024 consent agenda, approved 5-0 except for one unrelated item, included item 8.QQ, the purchase of two Fairbank Morse pumps for Lift Station 40 from AAW Pumps Motors Controls (BuyBoard[21][22]

      Purchase
      $90,275
    • ✓ Verified

      The agenda item does not state a reason for the purchase or refer to the 2023-2024 overflows at Lift Station 40; no public statement connecting them was found.[21]

  14. · Related development

    Force main break at Lift Station 40 releases about 1 million gallons

    The City reported about 1 million gallons of untreated wastewater discharged from Lift Station 40 at 7100 Cliffside from 4:15 p.m. to 10:15 p.m. on July 9, 2025, after a break in the force main caused the station to overflow from a manhole. Wastewater may have reached a ponded area of West Amarillo Creek; tests were being conducted. TCEQ was notified.[23][24]

    • ✓ Verified

      The City reported that about 1 million gallons of untreated wastewater discharged from Lift Station 40 at 7100 Cliffside from 4:15 p.m. to 10:15 p.m. on July 9, 2025, caused by a break in the force main that made the station overflow from a manhole.[23][24]

      Gallons approx
      1,000,000
    • ✓ Verified

      The City said the wastewater may have reached a local ponded area of West Amarillo Creek, that tests were being conducted for contamination, that land-surface remediation and disinfection were complete, and that TCEQ had been notified.[23][24]

  15. · Context

    Council awards $80,862 for communication upgrades at lift stations

    On consent (approved 5-0), the council awarded Sentinel Power, Inc. $80,862 for communication upgrades to lift stations throughout the wastewater collection system, funded from water and sewer fund revenues.[25]

    • ✓ Verified

      On March 10, 2026 the council approved its consent agenda 5-0 (except item 5.6), including item 5.15, an $80,862 award to Sentinel Power, Inc. for communication upgrades to lift stations throughout the wastewater collection system, funded from water and sewer fund revenues.[25]

      Contract
      $80,862
  16. · Context

    Council approves $55,853.80 for pumps and motors at Lift Station 16

    On consent (approved 4-0), the council approved buying two motors and two pumps for Lift Station 16 from Austin Armature Works through BuyBoard for $55,853.80; the item said the pumps had reached the end of their life.[26]

    Austin Armature Works

    • ✓ Verified

      On April 28, 2026 the council approved its consent agenda 4-0, including item 4.10, the purchase of two motors and two pumps for Lift Station 16 from Austin Armature Works (BuyBoard[26]

      Purchase
      $55,854
  17. · Trigger

    About 750,000 gallons discharged from a sewer main near East Amarillo Creek

    The City reported that a sewer main failure discharged about 750,000 gallons of untreated wastewater from a manhole just east of East Amarillo Creek, between West and East Chaparral Road. Water Utilities was notified at 11:30 a.m. and stopped the discharge at 3:25 p.m. The wastewater reached the creek and possibly flowed toward Thompson Park Lake; the City advised against recreational contact in the lake and part of the creek and notified TCEQ.[27][28][29]

    • ✓ Verified

      The City estimated about 750,000 gallons of untreated wastewater discharged from a sewer main manhole east of East Amarillo Creek, between West and East Chaparral Roads; Water Utilities was notified at 11:30 a.m. on September 11, 2026 and stopped the discharge at 3:25 p.m.[27][28][29]

      Gallons
      750,000
    • ✓ Verified

      The City said the wastewater reached East Amarillo Creek and was possibly flowing toward Thompson Park Lake, advised temporarily stopping recreational contact (wading, paddling, kayaking and fishing) in Thompson Park Lake and East Amarillo Creek between West Chaparral Road and West Hastings Avenue, said laboratory samples would be collected after repairs, and said TCEQ had been notified.[27][28]

    • ✓ Verified

      The City's release describes a sewer main failure but does not state its cause or give a timeline for completing repairs or lifting the advisory. As of October 10, 2026 no City release or news report was found reporting the cause, repair completion, lab results or the advisory being lifted.[27][30]

  18. · Related development

    Pump malfunction at Lift Station 40 releases about 200,000 gallons

    The City reported about 200,000 gallons of untreated wastewater discharged at Lift Station 40, 7100 Cliffside Road, from 12:30 p.m. to 3:15 p.m. on September 20, 2026, after a pump malfunction caused the station to overflow from a manhole. It did not reach natural waterways; repairs and disinfection were completed and TCEQ was notified.[31][32][33]

    • ✓ Verified

      The City reported about 200,000 gallons of untreated wastewater discharged at Lift Station 40, 7100 Cliffside Road, from 12:30 p.m. to 3:15 p.m. on Sunday, September 20, 2026, caused by a pump malfunction that made the station overflow from a manhole; it did not reach natural waterways, and repair, remediation and disinfection were completed.[31][32][33]

      Gallons
      200,000
    • ✓ Verified

      City releases and local news report five overflows at the Lift Station 40 / 7100 Cliffside site between December 2023 and September 2026, of about 1,026,000 (reported December 11, 2023), 100,000 (July 2, 2024), 945,000 (September 16-17, 2024), 1,000,000 (July 9, 2025) and 200,000 gallons (September 20, 2026).[17][18][19][23][31]

      Overflow count
      5
  19. · ContextScheduled

    Lift Station 19 replacement study and $320,000 budget transfer on the October 13 agenda

    The October 13, 2026 council agenda lists a $320,000 transfer from the Wastewater System Improvements & Repairs capital project to a new Lift Station 19 Relocation Design project, and a $319,260 professional services contract with HDR Engineering for a Phase 1 alternatives evaluation and preliminary design of a Lift Station 19 replacement, including evaluating consolidation of Lift Stations 16 and 25.[34][35]

    Jerry DanforthHDR Engineering, Inc.

    • Pending

      The October 13, 2026 agenda packet requests a $320,000 transfer from PRJ-0000132 (Wastewater System Improvements & Repairs, unobligated balance $1,299,330.51) to a new PRJ-0000259 (Lift Station[34][35]

      Transfer
      $320,000
      Source project unobligated
      $1,299,331
    • Pending

      The same agenda lists a $319,260 professional engineering services contract with HDR Engineering, Inc. (selected through RFQ 302-26) for a Phase 1 alternatives evaluation and preliminary design of a Lift Station 19 replacement, including evaluating consolidation of Lift Stations 16 and 25, flow monitoring and Quality Level D subsurface utility engineering. The council had not voted as of October 10, 2026.[34][35]

      Contract
      $319,260

Related storylines: Amarillo's wastewater plants: failures, enforcement, expansion financing and rate increases (2022-2026)