· Context
Change order brings the FY2017-18 pipe-bursting sewer rehabilitation contract to $2,103,134
The June 9, 2020 consent agenda included Change Order No. 3 ($18,620) to the FY2017-2018 Sewer Main Rehabilitation by Pipe Bursting contract with PM Construction & Rehab LLC dba IPR South Central, raising it from an original $1,886,030 to $2,103,134, for additional sewer main replacement near Oldham Circle and Southwest 32nd Avenue.[1]
What the sources say
- ✓ Verified
The June 9, 2020 minutes list, among consent items moved for approval as presented, Change Order No. 3 ($18,620) to the FY2017-2018 Sewer Main Rehabilitation by Pipe Bursting contract with PM Construction & Rehab LLC dba IPR South Central: original contract $1,886,030, previous change orders $198,484, revised total $2,103,134. The scanned minutes page does not show a vote tally for the consent agenda.[1]
- Original contract
- $1,886,030
- Revised contract
- $2,103,134
- Previous change orders
- $198,484
- Change order 3
- $18,620