· Context
Lift Station 19 replacement study and $320,000 budget transfer on the October 13 agenda
Pending Scheduled; has not yet occurred.
The October 13, 2026 council agenda lists a $320,000 transfer from the Wastewater System Improvements & Repairs capital project to a new Lift Station 19 Relocation Design project, and a $319,260 professional services contract with HDR Engineering for a Phase 1 alternatives evaluation and preliminary design of a Lift Station 19 replacement, including evaluating consolidation of Lift Stations 16 and 25.[1][2]
Jerry DanforthHDR Engineering, Inc.
What the sources say
- Pending
The October 13, 2026 agenda packet requests a $320,000 transfer from PRJ-0000132 (Wastewater System Improvements & Repairs, unobligated balance $1,299,330.51) to a new PRJ-0000259 (Lift Station[1][2]
- Transfer
- $320,000
- Source project unobligated
- $1,299,331
- Pending
The same agenda lists a $319,260 professional engineering services contract with HDR Engineering, Inc. (selected through RFQ 302-26) for a Phase 1 alternatives evaluation and preliminary design of a Lift Station 19 replacement, including evaluating consolidation of Lift Stations 16 and 25, flow monitoring and Quality Level D subsurface utility engineering. The council had not voted as of October 10, 2026.[1][2]
- Contract
- $319,260