Storyline · 26 events · Nov 2016 – Sep 24, 2026
Financing the Amarillo Civic Center expansion and renovation (2016-2026)
In November 2016 Amarillo voters rejected a Civic Center expansion bond proposition while approving street and public-safety bonds. A $319 million Civic Center plan followed in 2019-2020; the council called a $275 million general obligation bond election, and voters rejected that Proposition A on November 3, 2020. On May 24, 2022 the council approved $260 million in tax anticipation notes for the project. A local businessman sued; on October 25, 2022 the trial court voided the approval and awarded him attorney fees. The Seventh Court of Appeals affirmed on August 16, 2023, and the City's petition to the Supreme Court of Texas was dismissed on its own motion on December 8, 2023. In 2025-2026 the council approved Civic Center repair and improvement contracts, including a $1.85 million Coliseum restroom renovation and a $422,770 boiler replacement funded by the Amarillo-Potter Events Venue District, and a $166,746 basketball court; the proposed FY2026-27 budget sets the General Fund transfer to the Civic Center Improvement Fund at $3,692,099.
A storyline groups dated events in order. It is a chronology, not an argument; it does not say why anything happened. All storylines
- City buildings
- Construction & streets
- Budget & taxes
- Debt & financing
- Courts & law
- Votes & elections
- Downtown & development
- Contracts & procurement
- Leadership & governance
· Origin
Voters reject a Civic Center expansion bond in a seven-proposition package; streets and public safety pass
Amarillo voters approved two of seven City capital-improvement bond propositions: street improvements ($89.5 million) and public safety ($20.1 million). Five propositions totaling $230 million failed, including one for the Amarillo Civic Center. Texas Scorecard reported the Civic Center proposition at $83.4 million.[1][2]
- ✓ Verified
In November 2016 Amarillo voters approved two of seven City bond propositions (streets and public safety); five propositions totaling $230 million failed, including one for the Amarillo Civic Center.[1][2]
- Propositions total
- 7
- Passed
- 2
- Failed
- 5
- Failed total
- $230,000,000
- ⚠ Sources differ
Reported amounts of the two approved 2016 propositions differ slightly by source.
- ✓ Verified
City of Amarillo press release (Nov. 9, 2016), as reported by HPPR: The City said the two approved 2016 propositions would be funded through tax-supported debt repaid over five years.[1]
· Context
City schedules a $6 million-plus Civic Center roof replacement, mostly insurance-funded
The City announced replacement of the hail-damaged Civic Center roof and drainage system, a project of more than $6 million with about 95% covered by an insurance settlement and the rest by the City. The report noted a committee was assessing the complex's future, including a new facility with a larger arena.[4]
- ✓ Verified
The Civic Center roof replacement was reported at more than $6 million, with an insurance settlement covering about 95% and the City covering the rest; the roof was damaged in a 2017 hailstorm.[4]
- Total usd min
- $6,000,000
- Insurance share
- 95%
· Context
City unveils a $319 million Civic Center redevelopment proposal
The City presented a $319 million proposal including Civic Center renovations, a new arena, relocation of City Hall, a central park, Santa Fe Depot renovation and a parking structure, with public forums scheduled for September 2019 and a bond election anticipated for May 2020.[3]
- Unverified
Texas Scorecard: Texas Scorecard reported that the City's $319 million proposal called for $279 million in new taxpayer-supported debt, a roughly $155 million 10,000-seat arena, and an estimated tax increase of $150 per year on a $100,000 home.[3]
- Project
- $319,000,000
- Proposed debt
- $279,000,000
- Arena
- $155,000,000
· Precursor
Citizen committee recommends the $319 million Civic Center project to the council
At a council work session, a citizen executive committee recommended a $319 million project (exhibit space, a 10,100-seat arena, a new ballroom, Santa Fe Depot renovation and an expanded central plaza) to be funded by voter-approved debt.[5]
- ✓ Verified
On January 21, 2020 a citizen executive committee recommended to a council work session a $319 million Civic Center project to be funded by voter-approved debt, with a council vote set for February 11.[5]
- Project
- $319,000,000
- Arena seats
- 10,100
· Precursor
Council votes 5-0 to call a $275 million Civic Center bond election
The council voted 5-0 to call a May 2, 2020 election on $275 million in general obligation bonds toward the $319 million project, with $21 million in certificates of obligation (not requiring voter approval) and a projected 15-cent property tax rate increase.[6][7]
- ✓ Verified
The council voted 5-0 on a resolution calling a May 2, 2020 bond election on $275 million in general obligation bonds for the $319 million Civic Center project.[6][7]
- Vote for
- 5
- Vote against
- 0
- Go bonds
- $275,000,000
- Project
- $319,000,000
- ✓ Verified
The 2020 financing plan paired the $275 million in voter-approved bonds with $21 million in certificates of obligation (which do not require voter approval), $8 million from utilities and $15 million from value engineering; the tax impact was put at 15 cents on the rate, or $150.85 a year on a $100,000 home.[6]
- Project
- $319,000,000
- Go bonds
- $275,000,000
- Certificates of obligation
- $21,000,000
- Utilities
- $8,000,000
- Value engineering
- $15,000,000
- Tax rate increase cents
- 15
- ✓ Verified
Michelle Bonner, Deputy City Manager and CFO: Deputy City Manager and CFO Michelle Bonner said, "The general obligation bonds will go to the voters and there will be one proposition."[6]
· Related development
Voters reject Proposition A, the $275 million Civic Center bond
Proposition A, a $275 million bond for the Civic Center and related downtown projects, was defeated in the November 3, 2020 election. Mayor Ginger Nelson said, "I heard the voters say not now, not in this package, and I respect that result."[8][9][10]
- ✓ Verified
Mayor Ginger Nelson: Mayor Ginger Nelson said: "I am disappointed that our civic center proposal didn't pass" and "I heard the voters say not now, not in this package, and I respect that result."[9]
- ✓ Verified
By December 2020 Mayor Nelson had created a committee to look for ways to fund renovations without property tax increases, and a private group (Inspire Amarillo) proposed an alternative 'Amarillo Plan' it said would require a 15.9 percent city property tax increase.[10]
· Starting point
Council votes 4-1 to approve $260 million in tax anticipation notes for the Civic Center
The council approved $260 million in tax anticipation notes for a plan to add an arena, rehabilitate the Civic Center and restore the Santa Fe Depot. The City said the notes would raise the property tax rate from 44 cents to 57 cents per $100 of valuation.[11][12][13][14][15]
- ✓ Verified
On May 24, 2022 the council voted 4-1 to approve $260 million in tax anticipation notes for the expansion and renovation of the Civic Center.[12][11][14]
- Vote for
- 4
- Vote against
- 1
- Amount
- $260,000,000
- ✓ Verified
City of Amarillo, as reported by NewsChannel10: The City said the notes would raise the property tax rate from 44 cents to 57 cents, about $9 more per month on a home appraised at $100,000.[11]
- Rate before cents
- 44
- Rate after cents
- 57
- Monthly cost per 100k home
- $9
- ✓ Verified
ABC7 Amarillo: ABC7 reported that Cole Stanley, mayor at the time of the 2023 appeals ruling, was on the council when the plan was approved over his objections.[15]
- ✓ Verified
Mayor Ginger Nelson: Mayor Ginger Nelson said the project would reduce the Civic Center operating subsidy and that acting quickly to lock in the current interest rate would save money: "The longer we wait, this problem just continues to grow in cost."[12]
- Status
- approved, then voided before issuance
Coverage describes council approval of the notes and a court voiding that approval; a lawsuit sought to enjoin issuance.
Reported value 2[17]
- Status
- sold
A June 2023 Bond Buyer article states that in 2022 Amarillo 'sold $260 million in TANs.'
- ✓ Verified
NewsChannel10 (KFDA): NewsChannel10 reported that council members who supported the plan hoped private partners would help pay costs, for example through naming rights.[13]
· Trigger
A local businessman sues to block the tax anticipation notes
A local businessman and property owner sued the City, alleging the council approved the notes without notice to taxpayers of the debt terms and the taxes pledged to repay it, and sought a temporary injunction against issuing the debt.[16][13]
· Peak
Trial court voids the note approval and orders the City to pay the plaintiff's legal fees
In the 320th District Court (Potter County), visiting Judge William Sowder voided the May 24, 2022 approval, finding insufficient notice of the meeting's subject and that new Civic Center construction was not a "public work" eligible for tax anticipation notes. The City was ordered to pay the plaintiff's attorney fees.[18][16][19][20]
- ✓ Verified
Judge William Sowder voided the council's May 24, 2022 approval of the notes, finding insufficient notice of the meeting's subject, and held that using the proceeds was not authorized under the Texas Government Code because new construction of the Civic Center complex "is not a public work."[16][14]
- ⚠ Sources differ
The City was ordered to pay the plaintiff's attorney fees; reported amounts differ.[19][21][16]
Reported value 1[19]
- Amount usd min
- $375,000
- Conditional additional
- $30,000
October 2022 report of the trial judgment: more than $375,000, plus a possible $30,000 more if the case went to the Court of Appeals and he prevailed.
Reported value 2[21]
- Amount usd min
- $300,000
August 2023 report of the appeals ruling: 'more than $300,000' in attorney fees.
- ✓ Verified
City of Amarillo: The City said it "respectfully disagrees with the judgment" and was reviewing the decision with legal counsel.[16]
· Related development
City files notice of appeal to the Seventh Court of Appeals
The City appealed; the plaintiff also cross-appealed. Mayor Ginger Nelson said the City was "seeking clarification on existing state law" and that the lawsuit's delay had made the project infeasible given higher construction costs and interest rates.[18][14][15]
- Date
- 2022-11-10
- Milestone
- notice of appeal filed
Court docket and Bond Buyer: notice of appeal filed November 10, 2022 (after a November 4 motion to correct the judgment).
Reported value 2[15]
- Month
- 2023-02
- Milestone
- 'the city appealed in February'
ABC7 (Aug 2023) says the City appealed in February; the docket shows appellant's brief filed February 1, 2023.
- ✓ Verified
Mayor Ginger Nelson: Mayor Ginger Nelson said, "We are seeking clarification on existing state law," and said the lawsuit "created a delay to the point where the project isn't feasible."[14]
· Context
Governor vetoes a bill limiting non-voter-approved debt after failed bond elections
SB 2035, filed after the Amarillo lawsuit, would have barred tax anticipation notes and certificates of obligation for five years in place of bonds voters had rejected for the same purpose. Gov. Greg Abbott vetoed it, saying it had "too many loopholes."[17]
- ✓ Verified
SB 2035 by Sen. Paul Bettencourt, which followed the Amarillo lawsuit, passed the Senate 25-6 and the House 102-42 and would have barred tax anticipation notes and certificates of obligation for five years in place of bonds rejected by voters for the same purpose; Gov. Greg Abbott vetoed it on June 13, 2023, saying it "has too many loopholes."[17]
- Senate vote
- 25-6
- House vote
- 102-42
- Ban years
- 5
- ✓ Verified
Texas Attorney General; City of Amarillo: A brief by Attorney General Ken Paxton in the appeal said Amarillo "thwarted the will of the voters"; the City argued Texas law does not require voter approval for tax anticipation notes or refunding bonds.[17]
· Resolution
Seventh Court of Appeals affirms the judgment against the City
The Seventh Court of Appeals (No. 07-22-00341-CV, opinion by Justice Lawrence M. Doss) affirmed the trial court. Mayor Cole Stanley said he could not speak directly about the case while it remained in litigation.[18][15][21]
- ✓ Verified
NewsChannel10 (KFDA): NewsChannel10 reported the appeals court found the City violated Open Meetings Act rules in passing the plan.[21]
- ✓ Verified
Mayor Cole Stanley: Mayor Cole Stanley said he could not speak directly about the case because it was still in litigation, and that the council was discussing how to upgrade or repair the Civic Center.[15]
· Resolution
Supreme Court of Texas dismisses the City's petition on the City's own motion
The City filed a petition for review (No. 23-0797) on November 1, 2023, then filed an unopposed motion to dismiss on December 1, 2023. The Court granted the motion and dismissed the petition on December 8, 2023; the appeals court issued its mandate December 28, 2023.[22][18]
- ✓ Verified
The City filed a petition for review (No. 23-0797) on November 1, 2023 and an unopposed motion to dismiss on December 1, 2023; the Supreme Court of Texas granted the motion and dismissed the petition on December 8, 2023. The Court issued no opinion.[22]
- ✓ Verified
The Seventh Court of Appeals issued its mandate on December 28, 2023.[18]
- ✓ Verified
No fetched source reports a City statement explaining why it moved to dismiss its own petition.[22]
· Context
Council approves a $94,202.63 emergency repair of the Civic Center ice plant
On January 14, 2025 the City Council approved, on its 5-0 consent agenda, an emergency purchase of services and parts from Arena Products & Services LLC for $94,202.63 to repair the Civic Center's ice plant, funded from general fund revenues.[23]
Jerry DanforthArena Products & Services LLC
- ✓ Verified
On January 14, 2025 the council's consent agenda, approved 5-0, included an emergency purchase of services and parts for an emergency repair of the Civic Center's ice plant, awarded to Arena Products & Services LLC for $94,202.63 and funded from general fund revenues. [23]
- Amount
- $94,203
· Context
Council awards $1,846,147 Coliseum restroom renovation from Venue District funds
On June 10, 2025 the City Council voted 5-0 to award the renovation of the Civic Center Coliseum restrooms to Tri-State General Contracting Group, Inc. through a Sourcewell cooperative contract for $1,846,147, funded from Amarillo-Potter Events Venue District funds. A $97,281.07 change order on March 10, 2026 brought the total award to $1,943,428.07.[24][25]
Jerry DanforthTri-State General Contracting Group, Inc.
- ✓ Verified
On June 10, 2025 the council voted 5-0 to award the Civic Center Coliseum restroom renovation to Tri-State General Contracting Group, Inc. (Sourcewell contract TX-R4-GC-052124-JRT) for $1,846,147, funded from Amarillo-Potter Events Venue District funds. The item was set aside so a councilmember could review the contract during a recess, then approved later in the meeting. [24]
- Amount
- $1,846,147
- ✓ Verified
On March 10, 2026 the council approved Change Order No. 1 to the restroom renovation, $97,281.07 for additional structural support to remove and replace part of the concrete slab in the Coliseum's West Concourse, bringing the total award to $1,943,428.07 (Venue District fund revenues, CIP PRJ-440686). [25]
- Change order
- $97,281
- Total award
- $1,943,428
- ✓ Verified
The FY2026-27 proposed budget book states that renovation of the eight Coliseum restrooms, originally built in 1968, "is nearly complete." [26]
· Context
Council approves Civic Center temporary staffing contract funded by event revenue and hotel tax
On July 8, 2025 the City Council voted 3-0 to approve a temporary staffing services contract for the Civic Center with HireQuest, not to exceed $250,000 per year (up to $1,250,000 over five years), with event revenues and hotel occupancy taxes listed as the funding source.[27]
Cole StanleyDavid PrescottLes Simpson
- ✓ Verified
On July 8, 2025 the council voted 3-0 (Cole Stanley, David Prescott, Les Simpson) to approve a temporary staffing services contract for the Civic Center with HireQuest for an initial three years with two one-year renewals, not to exceed $250,000 per year or $1,250,000 over five years. The listed funding source was "Civic Center event revenues and Hotel Occupancy Taxes." The same item had been removed from the June 24, 2025 consent agenda with no action taken. [27][28]
- Annual cap
- $250,000
- Five year cap
- $1,250,000
· Context
Council approves a $79,174 Civic Center Entrance 4 soffit and lighting replacement
The City's planner listed for the August 12, 2025 meeting a $79,174 construction award to replace the soffit and lighting at Civic Center Entrance 4, funded from Civic Center building improvement funds. The council approved it on its August 12, 2025 consent agenda, 5-0.[29][30]
- ✓ Verified
The City's agenda planner listed for August 12, 2025 a $79,174 award to Wiley Hicks, Jr., Inc. (Tex-Buy 023-086) to replace the soffit and lighting at Civic Center Entrance 4, funded from Civic Center Building improvement funds and marked as budgeted.[29]
- Amount
- $79,174
- ✓ Verified
The council approved the $79,174 Entrance 4 soffit and lighting replacement award to Wiley Hicks, Jr., Inc. (Tex-Buy 023-086), funded from Civic Center building improvement fund revenues, as item 7.T of its August 12, 2025 consent agenda, which passed 5-0. [30]
- Amount
- $79,174
· Context
Council agenda planner lists a discussion of Civic Center improvements and a concession agreement
The City's planner listed for the September 9, 2025 meeting a discussion of improvements to the Civic Center Complex and a concession agreement guaranteeing the City a minimum of $500,000 per year. The planner does not record outcomes. On September 23, 2025 the council voted 5-0 to approve the concession agreement with Corkscrew Foods.[31][32]
- ✓ Verified
The City's agenda planner listed for September 9, 2025 a discussion of improvements to the Civic Center Complex and a revenue-only concession agreement with Corkscrew Foods guaranteeing a minimum of $500,000 per year ($2,000,000 over an initial four years, with two 2-year extensions for an additional $2,000,000).[31]
- Annual minimum
- $500,000
- Initial term years
- 4
- Initial minimum
- $2,000,000
- Extension minimum
- $2,000,000
- ✓ Verified
On September 23, 2025 the council voted 5-0 to approve a concession revenue agreement with Corkscrew Foods for concession sales throughout the Civic Center Complex: an initial four-year term with two two-year options, with a guaranteed minimum of $500,000 per year ($2,000,000 over the initial term plus an additional $2,000,000 over the extensions). The item had been competitively bid. [32]
- Annual minimum
- $500,000
- Initial term minimum
- $2,000,000
· Context
Council approves $166,746 purchase of a new Civic Center basketball court
On October 28, 2025 the City Council approved, on its 5-0 consent agenda, the purchase of a new modular basketball court for the Civic Center Complex from RFS Sports through a TIPS cooperative contract for $166,746, funded from Amarillo-Potter Event Venue District fund revenues.[33]
Bo FowlkesRFS Sports
- ✓ Verified
On October 28, 2025 the council's consent agenda, approved 5-0 (items 8.G and 8.O were pulled; this item, 8.K, was not), included the purchase of a new modular basketball court for the Civic Center Complex from RFS Sports (TIPS contract 24090701) for $166,746, funded from Amarillo-Potter Event Venue District fund revenues. [33]
- Amount
- $166,746
· Context
Council awards $422,770 Civic Center boiler replacement from Venue District funds
On November 18, 2025 the City Council approved, on its 5-0 consent agenda, a $422,770 award to Tri-State General Contracting Group, Inc. to remove and replace seven boilers, an expansion tank, a variable frequency drive and a hot water loop pump at the Civic Center, funded from Amarillo-Potter Events Venue District funds.[34]
Jerry DanforthTri-State General Contracting Group, Inc.
- ✓ Verified
On November 18, 2025 the council's consent agenda, approved 5-0, included a $422,770 award to Tri-State General Contracting Group, Inc. (Sourcewell TX-R4-GC-052124-JRT) for removal and replacement of seven boilers, an expansion tank, a variable frequency drive and a base-mounted hot water loop pump at the Civic Center, funded from Amarillo-Potter Events Venue District funds. [34]
- Amount
- $422,770
· Context
Council awards $63,871.31 Civic Center fire alarm replacement
On January 27, 2026 the City Council approved, on its 5-0 consent agenda, a $63,871.31 award to AV Corp. Fire & Security to replace the fire alarm system in the north end of the Civic Center, funded from Civic Center improvement fund revenues (CIP PRJ-0000128).[35]
- ✓ Verified
On January 27, 2026 the council's consent agenda, approved 5-0, included a $63,871.31 award to AV Corp. Fire & Security (TexBuy 025-010) to replace the fire alarm system in the north end of the Civic Center, funded from Civic Center improvement fund revenues (CIP PRJ-0000128). [35]
- Amount
- $63,871
· Context
City Manager memo describes the Civic Center as supported mainly by its own revenue and hotel tax
In a February 12, 2026 memorandum to the City Council framing a pre-budget workshop, City Manager Grayson Path wrote that the Civic Center Complex is not a General Fund department and is supported primarily through its own operating revenues and allocations of hotel occupancy tax, and recommended a separate, dedicated council discussion of the Civic Center rather than reopening the full debate at the workshop.[36]
- ✓ Verified
Grayson Path, City Manager (memorandum dated February 12, 2026): City Manager Grayson Path wrote that the Civic Center Complex "is not a General Fund department and is instead supported primarily through its own operating revenues and allocations of Hotel Occupancy Tax (HOT)," and suggested that if the council wished, it schedule a dedicated discussion at which staff could present "options for reducing the HOT subsidy through operational and fee strategies, along with capital and facility-planning scenarios." [36]
· Context
Council awards $204,503 Civic Center staging replacement and a restroom change order
On March 10, 2026 the City Council approved, on its 5-0 consent agenda, a $204,503 award to MityLite, Inc. for replacement staging components for the Civic Center (Civic Center Improvement Fund revenues) and a $97,281.07 change order to the Coliseum restroom renovation for structural work on a concrete slab in the West Concourse (Venue District fund revenues).[25]
Bo FowlkesMityLite, Inc.Tri-State General Contracting Group, Inc.
- ✓ Verified
On March 10, 2026 the council's consent agenda, approved 5-0 (item 5.6 was pulled; items 5.11 and 5.13 were not), included a $204,503 award to MityLite, Inc. (BuyBoard 789-25) for replacement staging components for the Civic Center, funded from Civic Center Improvement Fund revenues (CIP 440603), and Change Order No. 1 to the Coliseum restroom renovation. [25]
- Amount
- $204,503
· Context
Civic Center unveils a $166,746 basketball court
The Civic Center unveiled a new basketball court; ABC 7 reported its cost as $167,000 and its funding as the hotel occupancy tax, and the City put the cost at $166,746. General manager Christopher Post said the old court was "no longer really being able to be used" and the goal was "to maintain current operations."[37][38][33]
- ✓ Verified
Nearly 60 years after the Civic Center opened, it installed a new $167,000 basketball court; ABC7 reported the project was funded by the hotel occupancy tax, which is collected from visitors to the city.[37][38]
- Amount
- $167,000
- Funding source
- hotel occupancy tax
- ✓ Verified
Christopher Post, Civic Center general manager: Civic Center general manager Christopher Post said the main objective was "the need for the old court no longer really being able to be used" and "to maintain current operations because we don't want to lose current business"; asked about revenue, he said he did not have numbers in front of him.[37]
- ✓ Verified
The City's June 5, 2026 release said the new court cost $166,746 and that the original court, in use since the facility opened in 1968, was sold at online auction for $20,000, with the proceeds going to the Civic Center as revenue to help offset operating costs. [38]
- Court cost
- $166,746
- Old court auction
- $20,000
- ✓ Verified
Sources describe the court's funding in different terms: ABC7 reported it was funded by the hotel occupancy tax; the October 28, 2025 council minutes list "Amarillo-Potter Event Venue District fund revenues"; and the City's hotel tax page says a 2% hotel tax is imposed for the Amarillo-Potter Events Venue District. The City's June 2026 release does not state a funding source. [37][33][39][38]
· Context
Council approves Civic Center capital budget transfers for emergency repairs, IT and the basketball floor
The City's planner listed for the July 28, 2026 meeting a transfer of budget funds from Capital Projects PRJ-127 and PRJ-128 for a South Exhibit Hall loading-dock door and two grease traps. No amount is listed. The council approved it 5-0 on July 28, 2026, along with a second transfer from the boiler project to Civic Center IT access points/fiber and the new basketball floor (also 5-0).[40][41]
- ✓ Verified
The City's agenda planner listed for July 28, 2026 a Civic Center capital project budget transfer from PRJ-127 and PRJ-128 for emergency replacement of a South Exhibit Hall loading-dock door and two grease traps.[40]
- ✓ Verified
On July 28, 2026 the council voted 5-0 to approve the Civic Center capital project budget transfer from PRJ-127 and PRJ-128 for the South Exhibit Hall loading-dock door and two grease traps, presented by Interim General Manager Christopher Post. It also voted 5-0 to transfer budget from PRJ-440755 (Boiler & Expansion Tank Replacement) to PRJ-130 (Civic Center I.T. access points and fiber upgrades) and PRJ-440299 (Civic Center new basketball floor). The minutes give no dollar amounts for either transfer. [41]
· Context
Proposed FY2026-27 budget sets the General Fund transfer to the Civic Center Improvement Fund at $3,692,099
The City's FY2026-27 proposed budget book (after council review, September 24, 2026) lists the General Fund transfer to the Civic Center Improvement Fund at $4,490,541 (FY2022-23 actual), $2,892,992 (FY2023-24 actual), $3,420,630 (FY2024-25 actual), $3,028,387 (FY2025-26 budget and revised estimate) and $3,692,099 (FY2026-27 proposed). The book describes the inter-fund transfer program as including the transfer of excess hotel/motel tax to the Civic Center Improvement Fund.[26]
- ✓ Verified
The FY2026-27 proposed budget book lists the General Fund operating transfer to the Civic Center Improvement Fund (account SC92060) as $4,490,541 in FY2022-23, $2,892,992 in FY2023-24 and $3,420,630 in FY2024-25 (actuals), $3,028,387 budgeted and estimated for FY2025-26, and $3,692,099 proposed for FY2026-27, a 17.98% increase. The book describes the General Fund inter-fund transfer program as including "the transfer of excess hotel/motel tax to the Civic Center Improvement Fund"; it does not break the Civic Center line into hotel tax and other money. [26]
- Fy2022 23 actual
- $4,490,541
- Fy2023 24 actual
- $2,892,992
- Fy2024 25 actual
- $3,420,630
- Fy2025 26 budget
- $3,028,387
- Fy2026 27 proposed
- $3,692,099
- ✓ Verified
The budget book's Civic Center narrative lists planned work including completing the change from incandescent to LED lighting in the Heritage Ballroom, Regency Room and three north hallways, upgrading professional audio systems in the Civic Auditorium and Globe-News Center, replacing network fiber, switches and wireless access points, and installing a storefront-style wall along the east-west hallway between entrances 1 and 5. These are planned items, not completed work. [26]
Related storylines: Moving Amarillo City Hall into the renovated Amarillo Hardware building (2016-2025)Amarillo's property tax rate and voter-approved debt (2016-2026)Downtown catalyst projects: convention hotel, parking garage and the MPEV ballpark (2011-2026)Downtown TIRZ #1 and Local Government Corporation financing (2006-2026)